What is the Vantage Frontier campus in Shackelford County?
Vantage Data Centers announced Frontier on Aug. 19, 2025 as its largest investment to date, over $25 billion. The campus covers 1,200 acres in Shackelford County, Texas, with 10 data centers totaling 3.7 million sq ft and 1.4 GW. Vantage said the first building would be delivered in the second half of 2026.
At the December 2025 groundbreaking, Vantage's post called Frontier part of Oracle and OpenAI's Stargate expansion. The state filings place the buildings at 246 PR 1604, with an Abilene mailing address.
How much is registered with Texas for the Frontier campus?
Vantage filed all 11 buildings with the Texas Department of Licensing and Regulation (TDLR) on June 29 and 30, 2026. Ten data center buildings, TX301 to TX310, list $945 million to $1.315 billion each, $10.566 billion in all. An office building, TX311, lists $74 million. That makes $10.64 billion, the sum.
These are building cost estimates in state accessibility filings, and Vantage's $25 billion covers the whole campus. The biggest building is TX304, at $1.315 billion and 453,385 sq ft.
How far along is the Vantage Frontier campus?
Epoch AI, reading satellite images from Sept. 4, 2026, says the first five buildings have their shells and roofs done. It says cooling and backup generators are going in at three of them, and foundations are under way for two of the five buildings to the north. Epoch numbers the buildings in its own order, not by the state's building numbers.
The state filing for building 7, TX307 ($1.15 billion, 398,117 sq ft), lists an estimated start of Nov. 13, 2026 and an end of April 17, 2028. Building 6, TX306, lists Jan. 22, 2027. Epoch AI estimates the first building will be running by Aug. 2027.
Who is building the power plant for the Vantage Frontier campus?
VoltaGrid is building a natural gas power plant, ABI-1, at 299 FM 604 to feed the campus. A July 2025 state filing, prepared by Ramboll, covers 210 gas generators, 709 MW. VoltaGrid's bigger air permit, number 182467, names Jenbacher engines made by INNIO.
Texas mailed a preliminary decision on that permit on Sept. 22, 2026, the day after the governor's Sept. 21 letter pausing data center permits (FracTracker; Public Citizen).
On Nov. 6, 2026, VoltaGrid filed six more 3,000 sq ft operations buildings, for power blocks 5 to 10, with TDLR at $5,042,502. It filed the power block 4 building on Oct. 30 at $840,417.
Who gets what on the Vantage Frontier campus?
Vantage has not published a trade split. By the math on Turner & Townsend's data center cost index, about $5.1 billion of the $10.64 billion registered with Texas is electrical work, about $3.5 billion is pipes, heat and air, and about $958 million is the building shell. The gas plant comes on top, and we found no dollar figure for it.
Which firms are on the Vantage Frontier campus?
Vantage names Kiewit as general contractor, and Kiewit is the design firm on all 11 Vantage filings. TIC, The Industrial Company, a Kiewit company, holds the state stormwater permit for construction at the southeast corner of SH 351 and FM 604, the crossing where the campus and VoltaGrid's plant are going up; its coverage began Aug. 1, 2025, the day Epoch AI dates the start of land clearing. Raydon holds the one for VoltaGrid's service yard at the same crossing.
On the power side, state filings name VoltaGrid, its engine maker INNIO Jenbacher and Ramboll, which wrote its air filing. Angel Trevino Architecture and Architecture Underground designed VoltaGrid's buildings, and Ron Davis Consulting filed Vantage's 11 buildings for state accessibility review. The Albany News names Cresa as the firm VoltaGrid hired for its 25-acre service yard. 10 firms in all are on the list below.
How do the ways into the Vantage Frontier campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Frontier campus in Shackelford County | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | No electrical, mechanical or fire subcontractor is named on a public record yet, so most calls start with Kiewit or VoltaGrid |
Who should go after the Vantage Frontier campus?
| Electrical distributors and power reps | VoltaGrid's gas plant and Jenbacher engines, and Kiewit's 10 data center buildings, where about half the money is electrical by the math. |
|---|
| Site work, concrete and steel suppliers | TIC and Raydon hold the stormwater permits at SH 351 and FM 604, and buildings 6 to 10 are still early. |
|---|
| Mechanical, HVAC and plumbing reps | Kiewit is the builder of record; we found no mechanical or plumbing firm named yet, so ask Kiewit who has the work. |
|---|
What should you do next on the Vantage Frontier campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Vantage Frontier campus or VoltaGrid's ABI-1 plant in Shackelford County, Texas.
Questions people ask about the Vantage Frontier campus
How much does the Vantage Frontier campus cost?
Vantage says over $25 billion, its largest investment to date, for the whole campus. Its 11 building filings with Texas TDLR register $10.64 billion of building work, the sum. The biggest is TX304, at $1,315,000,000 and 453,385 sq ft.
Is the Frontier campus part of Stargate?
Vantage's December 2025 groundbreaking post calls Frontier part of Oracle and OpenAI's Stargate expansion. That is what the sources state; Vantage's own Aug. 2025 news release does not name Oracle or OpenAI.
Who is the general contractor on the Vantage Frontier campus?
Kiewit. Vantage names Kiewit Corporation as general contractor, and Kiewit is the design firm on all 11 Vantage building filings with Texas. 10 firms are named on the job, listed above.
Where is the Vantage Frontier campus?
In Shackelford County, Texas, near Albany. The state filings give 246 PR 1604 with an Abilene mailing address. VoltaGrid's power plant is at 299 FM 604, just south of where SH 351 meets FM 604.
When will the first Frontier building open?
Vantage said in Aug. 2025 that the first building would be delivered in the second half of 2026. We found no source saying it has opened. Epoch AI estimates the first building will be running by Aug. 2027.
How will the Frontier campus get power?
From its own natural gas plant, VoltaGrid's ABI-1. A July 2025 state filing covers 210 gas generators, 709 MW. A bigger air permit, number 182467, names Jenbacher engines and is still pending.
Is there a fight over the Frontier campus?
Two. Texas mailed a preliminary decision on VoltaGrid's air permit on Sept. 22, 2026, the day after the governor's Sept. 21 letter pausing data center permits (FracTracker; Public Citizen). And in Jan. 2026, county commissioners said heavy trucks keep running stoplights at Highway 351 and FM 604, and approved No Thru Traffic signs with fines up to $500.
How many people will build the Frontier campus?
Up to 6,500 workers could be on site at peak construction, and the campus is expected to create 250 full-time jobs with a $25 million yearly payroll (Albany News, July 2025). Vantage says more than 5,000 people across construction and operations.
What does Shackelford County get from the campus?
Vantage will pay the county $10 million a year in place of property taxes, which could raise the county's yearly budget by nearly 200% (Albany News, July 2025).
What happens next on the Vantage Frontier campus?
Building 7, TX307 ($1.15 billion), lists an estimated start of Nov. 13, 2026 and an end of April 17, 2028. Building 6, TX306, lists Jan. 22, 2027. VoltaGrid's air permit 182467 still needs a final decision.
How we built this list
We read every Shackelford County filing on Texas TDLR's public TABS register (29 in all, 15 for Frontier and VoltaGrid; read Nov. 18, 2026), TCEQ's air permit papers for VoltaGrid's ABI-1 plant, TCEQ's construction stormwater permits for the county, Vantage's news release and groundbreaking post, Epoch AI, FracTracker, Public Citizen and The Albany News, and kept each firm a record or a named source puts on this job. TIC's stormwater permit does not name the project; we list it because its site is the SH 351 and FM 604 corner where the campus and VoltaGrid's plant are going up, its coverage began the day Epoch AI dates the start of land clearing, and Kiewit, TIC's parent, is the campus builder. Left out: Vantage itself and Oracle and OpenAI (owner and users), a tax consultant, equipment brands named with no firm to call, a mechanical firm known only from a social media snippet, firms reported on other Texas data centers, and individuals on the filings. No electrical, mechanical, steel or fire subcontractor is named on a public record we could open. The $10.64 billion is the sum of the 11 Vantage filings; the trade split is the math on Turner & Townsend's published data center shares. Phones are each firm's own office line, except Architecture Underground's, the number it filed with the state, and Raydon's, from its federal motor carrier registration. First published Nov. 19, 2026. We'll update this page when a new filing, permit or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Vantage Data Centers: Frontier, a $25B mega campus in Texas (news release, Aug. 19, 2025)
- Vantage Data Centers groundbreaking post, reshared by Kiewit on LinkedIn (Dec. 2025)
- Texas TDLR TABS filings for Shackelford County (11 Vantage filings, June 29-30, 2026; VoltaGrid filings, April 28 to Nov. 6, 2026), read Nov. 18, 2026
- Texas TDLR TABS2026024102 (TX307), read Nov. 18, 2026
- Texas TDLR TABS2027005386 (VoltaGrid, Nov. 6, 2026), read Nov. 18, 2026
- TCEQ plain language summary, air permit 182467 (VoltaGrid ABI-1)
- TCEQ notice of application, air permit 182467
- TCEQ technical review, VoltaGrid standard permit 180842 (July 2025)
- VoltaGrid ABI-1 standard permit application, prepared by Ramboll (July 2025)
- TCEQ water quality general permit search, Shackelford County construction stormwater, read Nov. 18, 2026
- FMCSA company snapshot, Raydon Inc (USDOT 470354), read Nov. 18, 2026
- FracTracker Alliance: Texas data center permits after the governor's halt (Oct. 19, 2026)
- Public Citizen: data center permits issued by TCEQ after 9/21/2026
- Epoch AI: OpenAI Stargate Shackelford (read Nov. 18, 2026)
- The Albany News: Data center plans move forward in Shackelford County (July 24, 2025)
- The Albany News: Traffic continues to overwhelm rural roads (Jan. 15, 2026)
- Kiewit locations (read Nov. 18, 2026)
- ConstructConnect on Turner & Townsend's Data Center Cost Index (Sept. 2, 2026)