Who's building the Waldorf Astoria tower in Miami

Miami's 100-story Waldorf Astoria is Florida's first supertall, and its $426 million permit sat in plan review for 909 days.

By Porter Stanley. Updated .

The Waldorf Astoria Hotel & Residences in downtown Miami is a 100-story, 1,049-foot tower of nine stacked cubes at 300 Biscayne Blvd, Florida's first supertall. Its City of Miami master building permit declares $426 million of construction value; it was issued Nov. 12, 2024 to John Moriarty & Associates after 909 days in plan review. A separate $668 million construction loan, called the largest condo construction loan in Florida history, closed in June 2024. The tower reached level 85 by late August 2026, and the city issued two more post-tension permits on Nov. 16, 2026. 11 firms are named on the job; the list below has all 11.

$426MDeclared value on the city master building permit
$668MConstruction loan, closed June 2024
100Stories, 1,049 feet tall
11Firms named on the job

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 11 firms on the Waldorf Astoria Miami?

We list the 11 firms named on the Waldorf Astoria tower in downtown Miami, one row each, grouped by kind of firm, with where each name comes from.

1Permit on the recordNov 12, 2024

John Moriarty & Associates of Florida, Inc.

General contractor; holds the tower's master building permit for new construction of the hotel rooms, condos and parking garage, and the grade survey and paving permit on the Waldorf Astoria tower in downtown Miami

Waldorf Astoria Hotel & Residences Miami, 300 Biscayne Blvd (permit address 249 NE 3 St), Miami (Miami-Dade County), FL

Master building permit BD22007725001B001, $426,000,000 declared value, 1,740,922 sq ft, issued Nov. 12, 2024 after 909 days in plan review

Work: General contractor; holds the tower's master building permit for new construction of the hotel rooms, condos and parking garage, and the grade survey and paving permit

Who to call: John Moriarty & Associates of Florida, Inc.
John Moriarty & Associates office line
(Hollywood, FL)
(954) 920-8550

The opportunity: City of Miami permit BD22007725001B001: 'JOHN MORIARTY AND ASSOCIATES OF FLORIDA INC | NEW CONSTRUCTION: 26 OR MORE LODGING UNITS|MULTI-FAMILY (CONDO)|PARKING GARAGE-MULTIPLE FLOORS', total cost $426,000,000. The tall building record also lists John Moriarty and Associates as main contractor.

2Permit on the recordNov 26, 2024

Power Design, Inc.

Electrical contractor: new service, switchboards and sub-feeds, plus fire alarm, CCTV and low-voltage data, lightning protection, temporary power and pool electrical permits on the Waldorf Astoria tower in downtown Miami

Waldorf Astoria Hotel & Residences Miami, 300 Biscayne Blvd (permit address 249 NE 3 St), Miami (Miami-Dade County), FL

Main electrical permit BD22007725001E001, $42,681,000, issued Nov. 26, 2024; fire alarm permit $800,000; CCTV and low-voltage data permit $1,300,000

Work: Electrical contractor: new service, switchboards and sub-feeds, plus fire alarm, CCTV and low-voltage data, lightning protection, temporary power and pool electrical permits

Who to call: Power Design, Inc.
Power Design main line
(St. Petersburg, FL)
(727) 210-0492

The opportunity: City of Miami permit BD22007725001E001: 'POWER DESIGN INC | ... NEW SERVICE|SUB-FEEDS|SWITCHBOARD/CONTROL PANEL', total cost $42,681,000. Its newest permit on the tower, BD22007725059E001 for pool electrical, was issued Oct. 15, 2026.

3Permit on the recordDec 6, 2024

Jorda Mechanical Contractors (Jorda Enterprises, Inc.)

Mechanical (HVAC) contractor: chillers, cooling tower, ductwork and the stationary generator, plus louver and exhaust ventilation permits on the Waldorf Astoria tower in downtown Miami

Waldorf Astoria Hotel & Residences Miami, 300 Biscayne Blvd (permit address 249 NE 3 St), Miami (Miami-Dade County), FL

Main mechanical permit BD22007725001MA001, $25,000,000, issued Dec. 6, 2024; its newest exhaust ventilation permit was issued Oct. 7, 2026

Work: Mechanical (HVAC) contractor: chillers, cooling tower, ductwork and the stationary generator, plus louver and exhaust ventilation permits

Who to call: Jorda Mechanical Contractors (Jorda Enterprises, Inc.)
Jorda Mechanical office line
(Doral, FL)
(305) 262-0095

The opportunity: City of Miami permit BD22007725001MA001: 'JORDA ENTERPRISES INC dba JORDA MECHANICAL CONTRACTORS | A/C DRAIN|CHILLER|COOLING TOWER|AC CENTRAL / HEATING SYSTEM|...|STATIONARY GENERATOR (MECH)', total cost $25,000,000.

What is the Waldorf Astoria Miami?

The Waldorf Astoria Hotel & Residences is a 100-story tower at 300 Biscayne Blvd in downtown Miami. It is 1,049 feet tall, which makes it Florida's first supertall. That is the developer's figure; the tall building record lists 1,041 feet and 98 floors while it is still being built. City permits list it at 249 NE 3 St.

The tower is nine stacked cubes. The first three hold a 205-room Waldorf Astoria hotel, and cubes four to nine hold about 360 condos. The permit covers 1,740,922 sq ft, with a parking garage, restaurants, retail and a spa. The developer is Property Markets Group (PMG), with partners, under Hilton's Waldorf Astoria brand. The top penthouse was listed at $50 million in 2023.

How much does the Waldorf Astoria Miami cost?

No full construction cost has been published. The City of Miami master building permit declares $426,000,000 of construction value. That is the value declared to the city for the work on that permit.

A $668 million construction loan closed in June 2024, from Bank OZK and Related Fund Management. It was called the largest condo construction loan in Florida history. A loan pays for the build, but it is not the same as the cost.

Older stories say "over $1 billion." That figure is the developer's projected sales of the condos, not what it costs to build. The other permits at the tower's address, trade and site work together, add up to about $146 million more, the sum.

How far along is the Waldorf Astoria Miami?

Work started in 2022 with the foundation. The master permit sat in city plan review for 909 days before it was issued on Nov. 12, 2024. By August 2026 the tower had reached level 85 and the ninth and final cube. Topping off is expected by the end of 2026, and completion is set for 2028. The finish date has moved more than once.

About 600 workers are on site each day, a number expected to drop to 400 to 500 after topping off.

New permits keep coming. A $3,245,000 window permit was issued Oct. 20, 2026, emergency radio system permits on Nov. 12, and two post-tension permits to CapForm on Nov. 16.

Who is building the Waldorf Astoria Miami?

John Moriarty & Associates of Florida is the general contractor. It holds the $426,000,000 master building permit. Keller North America did the foundation work in 2022 on a $5,165,000 permit, and CapForm does the concrete forming and post-tension work on the floors.

The Sieger Suarez Architectural Partnership is the architect of record, and BAMO did the interiors.

Which trade firms are on the Waldorf Astoria Miami?

Power Design holds the main electrical permit, $42,681,000, plus fire alarm and CCTV permits. Jorda Mechanical holds the $25,000,000 mechanical permit for the chillers, cooling tower and generator.

TK Elevator holds 13 elevator permits worth $6,798,534 in all. Sprinklermatic holds the $5,250,000 fire sprinkler permit. Wilkinson Hi-Rise has the trash chute permit, and BrightView did the tree work at the site. 11 firms in all are on the list below.

Who PMG hired before

PMG keeps going back to John Moriarty & Associates: Moriarty built its Echo Aventura towers, Society Wynwood and Society Las Olas. Sieger Suarez, the Waldorf's architect, also designed PMG's newest Brickell tower, which Juneau Construction is building.

  • Juneau Construction Company: general contractor on One Twenty Brickell Residences, a 34-story condo tower at 120 SW 8th St, Miami, FL, broke ground 2025.
  • Sieger Suarez Architects: architect on One Twenty Brickell Residences, Miami, FL, 2025. Also on this job.
  • John Moriarty & Associates: general contractor on Society Las Olas Phase II, a 42-story, 563-unit apartment tower, Fort Lauderdale, FL, topped out 2025, delivery planned early 2026. Also on this job.
  • John Moriarty & Associates: general contractor on Society Wynwood, a 10-story, 318-unit mixed-use building at 2431 NW 2nd Ave (PMG with Greybrook), Miami, FL, 2022. Also on this job.
  • John Moriarty & Associates: general contractor on Echo Aventura, twin condo towers at 3250 and 3330 NE 188th St, Aventura, FL, completed about 2016. Also on this job.

These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.

How do the ways into the Waldorf Astoria Miami compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Waldorf Astoria tower in downtown MiamiEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Waldorf Astoria Miami?

Electrical distributors and gear repsPower Design's $42,681,000 electrical permit, with fire alarm and CCTV work, on a 100-story tower still pulling permits.
Mechanical, plumbing and fire protection repsJorda Mechanical's $25,000,000 mechanical permit, Sprinklermatic's $5,250,000 sprinkler permit and TK Elevator's 13 elevator permits.
Concrete, finish and building product suppliersCapForm's post-tension work, still getting permits in November 2026, and the finish work that runs to 2028.

What should you do next on the Waldorf Astoria Miami?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Waldorf Astoria tower at 300 Biscayne Blvd in downtown Miami.

Questions people ask about the Waldorf Astoria Miami

How much does the Waldorf Astoria Miami cost?

No full construction cost has been published. The City of Miami master building permit declares $426,000,000 of construction value, and a separate $668 million construction loan closed in June 2024.

Is the Waldorf Astoria Miami a $1 billion project?

Not as a cost. The "over $1 billion" in older stories is the developer's projected condo sales. The master permit declares $426,000,000 of construction value.

Who is building the Waldorf Astoria Miami?

John Moriarty & Associates of Florida is the general contractor and holds the master building permit. 11 firms are named on the job, listed above.

How tall is the Waldorf Astoria Miami?

It is 100 stories and 1,049 feet tall, Florida's first supertall tower.

Where is the Waldorf Astoria Miami?

It is at 300 Biscayne Blvd in downtown Miami, Miami-Dade County, Florida. City permits use the address 249 NE 3 St.

When will the Waldorf Astoria Miami be finished?

Topping off is expected by the end of 2026, and completion is set for 2028. The finish date has moved more than once.

How many people work on the Waldorf Astoria Miami?

About 600 workers a day, expected to drop to 400 to 500 after topping off.

What is in the Waldorf Astoria Miami?

A 205-room Waldorf Astoria hotel in the first three cubes and about 360 condos in cubes four to nine, with a garage, restaurants, retail and a spa.

Who is the electrical contractor on the Waldorf Astoria Miami?

Power Design holds the main electrical permit, $42,681,000, issued Nov. 26, 2024, plus fire alarm and CCTV permits.

What is the newest permit on the Waldorf Astoria Miami?

On Nov. 16, 2026 the city issued two post-tension permits to CapForm, $70,870 and $60,061. Emergency radio system permits came on Nov. 12.

What happens next on the Waldorf Astoria Miami?

The tower is expected to top off by the end of 2026, then finish work runs to 2028. We'll update this page when a new permit or firm appears.

How we built this list

We read the City of Miami's open permit data on Nov. 21, 2026: every permit under the tower's application, BD22007725, and every permit at its city address, 249 NE 3 St. We also read the tall building record, news on the tower and the loan, and each firm's own website. We kept each firm a city permit or the building record names on this tower. Permit values are what was declared to the city for that work, not what the firm is paid. The $146 million is the sum of every other permit at the tower's city address besides the master permit. Left out: the developer and its partners, the hotel brand, the lenders, the lawyers, the sales team, a portable toilet rental, and firms whose permits were for the old building and sales center on the site. Also left out because we found no website or main line on a firm site of their own: Professional Plumbing ($29,500,000 plumbing permit), GM&P Consulting and Glazing (eight window permits, $22,264,300), CMC Contractors (roof waterproofing), Custom Pool Systems (pool and spa), Safety Guys (debris netting), BDA Consulting and Solutions (emergency radio), City Engineering Contractors (paving and drainage), and the design firms Carlos Ott, CHM Structural Engineers, MG Engineering and EGS2. Phones are each firm's own line from its own site; Power Design, Wilkinson Hi-Rise and BrightView are head office lines, and Sieger Suarez and BAMO show no main line on their sites. First published Nov. 21, 2026. We'll update this page when a new permit or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 11 firms, free

All 11 firms on the Waldorf Astoria Miami

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.