What is being built in the White House ballroom project?
The White House ballroom is part of the East Wing Modernization Project at 1600 Pennsylvania Avenue NW in Washington, DC. The Executive Residence at the White House is the applicant, and the land is part of President's Park, run by the National Park Service.
The National Capital Planning Commission's staff report puts the project at about 89,000 sq ft over two floors above ground. The ballroom is about 22,000 sq ft, for about 1,000 seated guests. The project will not exceed the height of the Executive Mansion, about 60 feet. It also holds a commercial kitchen, an office suite for the First Lady and a replacement movie theater.
It is a federal project on federal land, reviewed by federal commissions; we found no DC building permit for it. The Commission of Fine Arts approved the final design on Feb. 19, 2026, and the National Capital Planning Commission approved the site and building plans (file 8733) on Apr. 2, 2026.
How much does the White House ballroom cost?
The public figure has changed over time: $200 million in July 2025, $300 million in October 2025 and $400 million in December 2025. The White House's public figure is about $400 million.
In June 2026, news reports said Clark Construction told the White House on March 5, 2026 that the project had grown to $600 million. That is Clark's internal estimate as reported, not a published contract value. As reported, that summary expected $293 million, nearly half, from private sources, and about $155 million from the Secret Service, about $149 million from the White House Military Office and about $3 million from the Executive Residence.
Clark's contract with the Executive Residence, signed Sept. 22, 2025, is worth up to $500 million. News reports say it was not competitively bid. A Clark spokesperson said all project details are confidential and referred questions to the White House.
Who is building the White House ballroom?
Clark Construction is the general contractor. In August 2025 the White House picked Clark and AECOM, with AECOM as engineer. On Nov. 4, 2026, Clark's workers were at the event for the last steel beam.
News reports say Clark planned to award no-bid deals to at least 11 subcontractors, two of them Clark subsidiaries, one of which is to provide concrete; those firms were not named in the reports we read. Firms that have been named: ACECO, a Maryland demolition company, had its name on an excavator photographed leveling the East Wing in October 2025; Carrier said it is providing the ballroom's HVAC system; and ArcelorMittal said it had delivered about 600 metric tons of steel by April 30, 2026.
Who designed the White House ballroom?
McCrery Architects was named the lead design firm in July 2025. Shalom Baranes Associates became the architect of record in December 2025, and a White House official said McCrery remains a consultant. AECOM is the engineer.
The drawings sent to the Commission of Fine Arts in February 2026 list five more consultants: M. Paul Friedberg & Associates (landscape), Curtainwall Design Consulting (envelope and fall protection), SM&W (acoustics, vibration and AV), Persohn/Hahn Associates (elevators and escalators) and Next Step Design (food service). 12 firms in all are on the list below.
How far along is the White House ballroom?
The steel frame topped out on Nov. 4, 2026, when the last steel beam was placed at an event with Clark Construction workers. In May 2026, President Trump said the ballroom should open around September 2028 and called it "ahead of schedule."
After new photos of the frame came out in November 2026, Hillary Clinton and Rep. Jim Clyburn criticized its size.
What is the court case over the White House ballroom?
The National Trust for Historic Preservation sued over the project in December 2025. In late March 2026, Senior U.S. District Judge Leon temporarily barred above-ground construction, and in August a divided appeals court panel upheld his order. On Aug. 31, 2026, the Supreme Court voted 5-4 to put that order on hold, so construction continues.
On Nov. 5, 2026, the Solicitor General asked the Supreme Court to reverse Judge Leon's ruling without a hearing, or to hear full arguments. The National Trust's response is due Dec. 7, 2026.
Who the White House hired before
Clark Construction already held the Executive Residence's maintenance and construction contract before the ballroom, and the Park Service then gave it a park job across the street.
- Clark Construction: builder on Lafayette Park fountain restoration (National Park Service, $17.4 million sole-source), Washington, DC, 2026. Also on this job.
- Clark Construction: builder on Executive Residence maintenance, repair, alteration and construction contract ($500 million ceiling, competitively bid), Washington, DC, 2024. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 12 firms on this job.
How do the ways into the White House ballroom compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the White House ballroom (East Wing Modernization Project) | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the White House ballroom?
| HVAC, mechanical and electrical reps | Clark Construction, the general contractor, and Carrier, which said it is providing the ballroom's HVAC system. |
|---|
| Steel, concrete and site suppliers | Clark Construction, ArcelorMittal on structural steel (about 600 metric tons by April 2026) and ACECO, whose equipment was photographed leveling the East Wing. |
|---|
| Interiors, kitchen, AV and elevator suppliers | The consultants on the federal review drawings: Next Step Design (food service), SM&W (acoustics and AV), Persohn/Hahn Associates (elevators and escalators) and Curtainwall Design Consulting (envelope). |
|---|
What should you do next on the White House ballroom?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the White House ballroom, also called the East Wing Modernization Project.
- Watch the Supreme Court case: the National Trust's response is due Dec. 7, 2026.
Questions people ask about the White House ballroom
How much does the White House ballroom cost?
Clark Construction's internal estimate rose to $600 million by March 2026, as reported in June 2026. The White House's public figure is about $400 million. Earlier public figures were $200 million in July 2025 and $300 million in October 2025.
Who is building the White House ballroom?
Clark Construction is the general contractor, with a contract of up to $500 million signed Sept. 22, 2025. AECOM is the engineer and Shalom Baranes Associates is the architect of record. 12 firms are named on the job, listed above.
Was the White House ballroom contract bid?
News reports say Clark's contract with the Executive Residence, signed Sept. 22, 2025 and worth up to $500 million, was not competitively bid. Clark also held an earlier Executive Residence contract from 2024 with a $500 million ceiling, which was competitively bid.
Who is paying for the White House ballroom?
As reported in June 2026, Clark's March 5, 2026 project summary expected $293 million, nearly half of its $600 million estimate, from private sources, and about $155 million from the Secret Service, about $149 million from the White House Military Office and about $3 million from the Executive Residence.
Who designed the White House ballroom?
Shalom Baranes Associates has been the architect of record since December 2025. McCrery Architects was the first lead design firm, and a White House official said it remains a consultant. AECOM is the engineer.
How big is the White House ballroom?
The project is about 89,000 sq ft over two floors above ground. The ballroom is about 22,000 sq ft, for about 1,000 seated guests, and the project will not exceed the height of the Executive Mansion, about 60 feet.
When will the White House ballroom open?
President Trump said in May 2026 that it should open around September 2028. The steel frame topped out on Nov. 4, 2026.
Is construction on the White House ballroom still going?
Yes. A lower court barred above-ground construction and an appeals court upheld that order, but the Supreme Court put it on hold on Aug. 31, 2026, so construction continues.
What is the Supreme Court case about the White House ballroom?
The National Trust for Historic Preservation sued over the project. On Nov. 5, 2026, the government asked the Supreme Court to reverse the lower court's ruling or hear full arguments. The National Trust's response is due Dec. 7, 2026.
Does the White House ballroom need a building permit?
We found no DC building permit: it is a federal project on federal land. It went through federal reviews instead: the Commission of Fine Arts approved the final design on Feb. 19, 2026, and the National Capital Planning Commission approved the plans on Apr. 2, 2026.
How can subcontractors get on the White House ballroom?
Call the firms already on the job, starting with Clark Construction, the general contractor. News reports say Clark planned to award no-bid deals to at least 11 subcontractors, but they were not named in the reports we read.
What happens next on the White House ballroom?
The National Trust's response to the Supreme Court petition is due Dec. 7, 2026, and work continues under the Court's stay. We'll update this page when a new record or firm appears.
How we built this list
We read the White House's Nov. 4, 2026 photo page, the Commission of Fine Arts submission and action, the National Capital Planning Commission's staff report and action, Sen. Blumenthal's June 17, 2026 letter to Clark Construction, and news reports from ENR, CBS News, The Washington Post (via the Anchorage Daily News and the Philadelphia Inquirer), USA Today, Eurometal, Yahoo News, SCOTUSblog and Dezeen, all on Nov. 24, 2026. We kept each firm a public record or news report names on this project. Six of the 12 come from the consultant list on the drawings sent to the Commission of Fine Arts. The $600 million is Clark's internal estimate as reported, not a published contract value; the $500 million is the contract's ceiling, not money spent. We found no DC building permit; it is a federal project on federal land, reviewed by the Commission of Fine Arts and the National Capital Planning Commission. Left out: the Executive Residence and the National Park Service (the owners), the National Trust for Historic Preservation (the plaintiff), the donors, a hauling firm seen only on one truck, the 11 or more subcontractors Clark planned to hire, two of them its own subsidiaries (not named in what we read) and the civil, MEP and structural engineers on the drawings (shown only as logos). Phones are each firm's own line from its own site; Carrier's is its commercial contact line, SM&W's its new business line and Curtainwall Design Consulting's its Dallas headquarters. AECOM, ArcelorMittal and Persohn/Hahn Associates show no line we could use, so we give their websites only, and we found no website or line for ACECO. First published Nov. 24, 2026. We'll update this page when a new record, ruling or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 24, 2026- White House: last piece of steel in the construction of the White House Ballroom (Nov. 4, 2026)
- SCOTUSblog: administration brings the White House ballroom case back to the Supreme Court (Nov. 10, 2026)
- Dezeen: White House ballroom topping out (Nov. 16, 2026)
- Sen. Blumenthal: letter to Clark Construction's CEO (June 17, 2026)
- USA Today report on the $600 million estimate, as posted by Rep. Katherine Clark's office (June 16, 2026)
- Anchorage Daily News (Washington Post): the $500 million contract (June 30, 2026)
- ENR: White House picks Clark and AECOM for the State Ballroom (Aug. 4, 2025)
- CBS News: some White House ballroom contractors go underground (Oct. 29, 2025)
- Commission of Fine Arts: East Wing Modernization submission (Feb. 2026)
- Commission of Fine Arts: East Wing Modernization action (Feb. 2026)
- NCPC: East Wing Modernization Project staff report (March 2026)
- NCPC: East Wing Modernization Project Commission action (Apr. 2, 2026)
- Eurometal: ArcelorMittal confirms steel supply for the White House ballroom (May 3, 2026)
- Yahoo News: the White House ballroom's price tag and opening date (May 15, 2026)
- ENR, 2026-04-27, White House ballroom contractor wins $17.4M sole-source park contract
- Philadelphia Inquirer / Washington Post, 2026-06-30