What is being built for California high-speed rail's first track?
The California High-Speed Rail Authority is about to lay its first track. The first package covers civil, track and overhead wire work on 22 miles of guideway in Kern County. It runs from about one mile north of the Tulare/Kern County line south to Wasco and Shafter. This stretch was ready first, so work starts there and then moves north toward Fresno.
The whole contract covers track, overhead wires, traction power, train control, communications and control systems for the 119-mile first section, from Shafter to Madera County. It has options to reach Merced and Bakersfield.
Materials come in by rail at the 150-acre Southern Railhead near Wasco. It has about 10 miles of temporary siding and storage track, built with BNSF Railway. In February 2026, the governor's office marked the railhead done and said about 80 miles of guideway and 58 structures were finished.
How much is the high-speed rail track contract?
The board approved the track and systems contract on June 1, 2026, with a ceiling of $3.5 billion. That is a limit, not money spent. The first two notices to proceed add up to $378.9 million: $260,843,101 for the first track package, a lump sum, and $118,110,340 for design and preconstruction.
Each later package needs its own board approval. The authority's program budget, approved in August 2025, is $36.75 billion.
The contract sets goals of 25% small business (3% micro), 10% disadvantaged business and 3% disabled veteran business. That is the opening for smaller subcontractors and suppliers.
When does track laying start?
The contract said to start laying track on or before Nov. 30, 2026. On Nov. 19, interim CEO Joe Stephenshaw said track laying is a matter of weeks away, with work expected around the middle to end of December. He took over after Ian Choudri resigned.
The builder was due to get access to the work area, including the railhead, on July 1, 2026. Kiewit Infrastructure West Co. filed the state stormwater permit for the work: 122.75 acres, from Aug. 10, 2026 to Oct. 4, 2027.
The first 22 miles of track are due by June 14, 2027. The overhead wires are due by Oct. 18, 2027.
Who won the high-speed rail track contract?
Kiewit, Stacy Witbeck, Herzog - A Joint Venture won. Only two teams sent proposals, and the other, California High Speed Partners, was found non-responsive. So the board voted on one team. California High Speed Partners filed a protest on May 5, and the authority answered it on May 13.
Board member Jeffrey Worthe objected to "locking ourselves" into a single bidder. The board approved the contract on June 1, 2026. Kiewit, Stacy Witbeck and Herzog are all rail builders.
Who supplies the rail, ties, ballast and poles?
The authority buys the main track materials itself and hands them to the builder. A&K Railroad Materials won the long welded rail at $81.9 million. It was the only bidder.
Rocla Concrete Ties, part of Vossloh, won the concrete ties at $52.6 million. Vossloh says that is 335,000 ties with fastenings, made in Pueblo, Colorado. The next bid was $99.1 million. Oldcastle Infrastructure won the cable troughs at $56.9 million, against a $103.1 million bid.
The ballast went to two suppliers. Deer Creek Asphalt is first-ranked at $50.1 million, and Vulcan Materials is second-ranked with at least 25% of the volume.
Engineered Pole Structures won the poles for the overhead wires at $25.9 million. Two lower bids, $13.5 million and $22.3 million, were found non-responsive. On Nov. 20, 2026, the authority proposed Graybar for the fiber optic cable, at a low bid of about $3.05 million on the main item.
Who else is on the high-speed rail track job?
The SYSTRA|TYPSA joint venture designs the track and overhead wire system. The board hired it on June 26, 2024. BNSF Railway built the railhead's storage track with the authority.
On Oct. 28, 2026, the board voted 8-0 for Siemens Mobility to build the first three trainsets, at a $281.7 million lump sum and up to $772.1 million with maintenance. The first trains are due in the Central Valley for testing by early 2030. Siemens builds the trains, not the track, so it is not on the list.
Up to 1,700 workers report to high-speed rail construction sites each day, across the whole program.
Is California high-speed rail running out of money?
The high-speed rail inspector general has warned the project could run out of money by 2027. Stephenshaw pointed to $1 billion a year from the state's Cap and Invest program through 2045. The track work is going ahead, but only $378.9 million of the $3.5 billion contract is committed.
Who the High-Speed Rail Authority hired before
The authority split its first 119 miles of civil work among three big joint ventures; the team whose 22 miles get the first track is Ferrovial and Griffith.
- Dragados-Flatiron Joint Venture: builder on Construction Package 2-3 (about 65 miles incl. the Hanford Viaduct), Fresno, Tulare and Kings counties, CA, 2015.
- Tutor Perini / Zachry / Parsons (TPZP): builder on Construction Package 1, 32 miles Madera to Fresno ($4.06B per Tutor Perini), Madera and Fresno counties, CA, 2013.
- California Rail Builders (Ferrovial and Griffith Company): builder on Construction Package 4, the 22 miles from the Tulare/Kern line to Wasco, Kern and Tulare counties, CA, 2016.
These are earlier or other jobs for the same owner. They are not counted in the 13 firms on this job.
How do the ways into the high-speed rail track job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on California high-speed rail's track and systems contract | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The later track packages | A place with the builders on the next packages north toward Fresno and Madera County | Builders, electrical and systems subcontractors | A share of a contract with a $3.5 billion ceiling | Each later package needs its own board approval, and only $378.9 million is committed |
Who should go after the high-speed rail track job?
| Rail, steel and track material suppliers | Kiewit, Stacy Witbeck and Herzog lay the track; A&K, Rocla (Vossloh), Oldcastle, Deer Creek Asphalt and Vulcan supply the rail, ties, troughs and ballast. |
|---|
| Electrical, power and communications reps | Overhead wires, traction power, train control and communications are all in the contract; Engineered Pole Structures has the poles and Graybar the fiber optic cable. |
|---|
| Small and certified subcontractors | The contract's goals are 25% small business, 10% disadvantaged business and 3% disabled veteran business, on a $3.5 billion ceiling. |
|---|
What should you do next on the high-speed rail track job?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on California high-speed rail's track and systems contract in Kern County.
- Watch for track laying to start around mid-to-late December, and for the next package approvals.
Questions people ask about California high-speed rail's first track
When will California high-speed rail start laying track?
The contract said on or before Nov. 30, 2026. On Nov. 19, 2026, interim CEO Joe Stephenshaw said it starts in a matter of weeks, around the middle to end of December, on 22 miles in Kern County.
Who is laying the track for California high-speed rail?
Kiewit, Stacy Witbeck, Herzog - A Joint Venture, approved by the authority's board on June 1, 2026. 13 firms are named on the job, listed above.
How much is the high-speed rail track contract?
Up to $3.5 billion, a ceiling, not money spent. So far $378.9 million is committed: $260.8 million for the first track package and $118.1 million for design and preconstruction.
Where is the first high-speed rail track being laid?
On 22 miles of finished guideway in Kern County, from about one mile north of the Tulare/Kern County line south to Wasco and Shafter. Materials are staged at the 150-acre Southern Railhead near Wasco.
How many teams bid on the high-speed rail track contract?
Two. The other team, California High Speed Partners, was found non-responsive, so the Kiewit, Stacy Witbeck and Herzog team won alone.
Who supplies the rail and ties for California high-speed rail?
The authority buys them itself. A&K Railroad Materials supplies the long welded rail ($81.9 million), and Rocla Concrete Ties, part of Vossloh, supplies 335,000 concrete ties ($52.6 million).
When will the first 22 miles of track be done?
The contract's dates are June 14, 2027 for the track and Oct. 18, 2027 for the overhead wires.
How can subcontractors get on the high-speed rail track job?
Call the builders and suppliers on the list. The contract sets goals of 25% small business, 10% disadvantaged business and 3% disabled veteran business, so the builders need smaller firms.
Is California high-speed rail running out of money?
The high-speed rail inspector general warned it could run out of money by 2027. The interim CEO points to $1 billion a year from Cap and Invest through 2045.
How we built this list
We read the authority's June 1, 2026 board memo and slides on the track and systems contract, its April 29 award notice, its materials page and the award notices for rail, ties, poles, cable troughs, ballast and fiber optic cable, its railhead factsheet, the Siemens and SYSTRA|TYPSA board resolutions, the state stormwater permit record, the governor's Feb. 3 release, Kiewit's and Vossloh's releases, and news reports, on Nov. 23, 2026. We kept each firm a public record names on this job. Contract values for joint ventures are for the whole team, not one firm's share. The materials contracts cover the whole 119-mile first section, not only the first 22 miles. Graybar's award is proposed, not signed. Left out: the owner, losing and non-responsive bidders, law, finance and advisory firms, a program-wide repair bench with no task tied to this work, the program manager (AECOM-Fluor), the trainset maker (Siemens Mobility, which builds the trains, not the track), and the builders of the guideway itself (Ferrovial and Griffith, shown under who the authority hired before). Phones are each firm's own line from its own site; Kiewit's is its Northern California district line from its locations page, Herzog, Vulcan and BNSF are headquarters lines, Engineered Pole Structures is matched by name, and we found no main line for SYSTRA, TYPSA or Deer Creek Asphalt. First published Nov. 23, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- CHSRA board memo: Track and Systems Construction Contract (June 1, 2026)
- CHSRA board slides: Track and Systems Construction Contract (June 1, 2026)
- CHSRA Notice of Proposed Award: Track and Systems Construction Contract (April 29, 2026)
- ABC10: California high-speed rail's new interim CEO outlines funding, construction plans (Nov. 19, 2026)
- Fresno Bee via Yahoo: CA high-speed rail OKs track contract (June 1, 2026)
- Governor's office: high-speed rail milestone, track installation to begin (Feb. 3, 2026)
- CHSRA: Southern Railhead factsheet (Jan. 29, 2026)
- Kiewit: California approves team to build nation's first true high-speed rail track and systems (June 3, 2026)
- CHSRA: Procurement of High-Speed Rail Materials (read Nov. 23, 2026)
- CHSRA Notice of Proposed Award: Long Welded Rail (Dec. 30, 2025)
- CHSRA Notice of Proposed Award: Concrete Ties (Feb. 17, 2026)
- Vossloh: Vossloh to equip first high-speed rail line in the USA (May 4, 2026)
- CHSRA Notice of Proposed Award: OCS Poles (March 12, 2026)
- CHSRA bid tabulation: OCS Poles (Jan. 16, 2026)
- CHSRA Notice of Proposed Award: Cable Troughs (April 17, 2026)
- CHSRA Notice of Proposed Award: Ballast (June 4, 2026)
- CHSRA Notice of Proposed Award: Fiber Optic Cables (Nov. 20, 2026)
- CHSRA Resolution HSRA 26-17: Siemens Mobility trainsets (Oct. 28, 2026)
- CHSRA Resolution HSRA 24-09: Track and OCS design services award (June 26, 2024)
- California State Water Board SMARTS: construction stormwater permits
- ATI article hanford-viaduct-high-speed-rail-who-gets-paid (CHSRA sources)
- Tutor Perini: California High-Speed Rail
- Ferrovial newsroom: CRB final girders on CP 4